How to install reinforcement for concrete footings

Learn how to install reinforcement for concrete footings to AS 2870 and AS 3600. Master trench mesh placement, bar chairs, lap lengths, and concrete cover.

Quick answer

To install reinforcement for concrete footings, suspend trench mesh and deformed bars on compliant plastic chairs at least 50mm above the trench base. Overlap mesh joints by 500mm, tie securely with 1.57mm annealed wire, and maintain 40mm to 65mm clearance from earth walls to meet AS 2870 requirements.

Skill level
Advanced
Time
4–8 hours for a standard residential footing run, depending on footing length, complexity, access, and reo schedule
Trade
Building & Construction
Updated
1 November 2026

Tools you will need

  • Knipex 99 14 250 - High Leverage Concreters Nippers
  • Makita DTR180Z 18V LXT - Cordless Rebar Tying Tool
  • Ox Tools Pro 5m - Metric Heavy Duty Tape Measure
  • Leica Geosystems Rugby 610 - Rotating Construction Laser Level
  • Hitachi / HiKOKI 16mm - Electric Rebar Cutter and Bender
  • Master Finish 600mm - Heavy Duty Bolt Cutters
  • Novoplas Trench Mesh Supports - Plastic Bar Chairs (50/65mm)

What is involved in installing reinforcement for concrete footings in Australia?

🧱 Installing reinforcement for concrete footings is a critical structural task that directly affects load transfer, crack control, and long-term footing performance. On Australian residential sites, correct reo placement requires accurate trench preparation, compliant cover, secure bar support, and installation in line with the engineer’s drawings, AS 3600 Concrete Structures, and relevant NCC and state requirements.

This guide covers practical site procedure for placing trench mesh, longitudinal bars, ligatures, laps, bar chairs and tie wire in strip footings and similar residential footing systems. Structural reinforcement layouts, bar sizes and lap requirements must always match the project engineering documentation.

What skill level is required for concrete footing reinforcement in Australia?

Advanced — Estimated time: 4–8 hours for a standard residential footing run, depending on footing length, complexity, access, and reo schedule

What tools are required for installing concrete footing reinforcement?

Reinforcement cutter/bender or portable reo bender suitable for bars up to 16 mm
Reo tying pliers / nips
Battery tie wire tool for larger footing runs
5 m tape measure
Laser level or dumpy level
Stringline and line pins
Shovels, trenching spades and trench cleaning tools
Bolt cutters for tie wire and light reinforcement trimming
Angle grinder with metal cutting disc where permitted and safe
Bar chairs spacer placement tool or hook
Marking paint / chalk
Wheelbarrow or material trolley
Lifting slings where using machine-assisted reo placement
PPE including gloves, safety glasses, steel-cap boots, hi-vis, hearing protection

What materials are needed for concrete footing reinforcement?

Engineer-specified reinforcement bars, typically N12, N16 or trench mesh to structural schedule
Ligatures/stirrups where detailed on drawings
Tie wire, typically annealed wire for hand tying
Bar chairs or spacer supports rated for footing use
Plastic or concrete cover spacers where required
Starter bars, dowels or L-bars where shown on plans
Trench mesh supports suitable for maintaining specified bottom cover
Blinding layer material if required, such as lean mix or compacted bedding
Marking paint for set-out confirmation
Inspection tags or hold-point documentation where required by builder/engineer

Safety Requirements

⚠️ Safety: Wear gloves, safety glasses, long sleeves, steel-cap boots and hearing protection when cutting or grinding reo.
⚠️ Reinforcing bar ends present impalement and laceration risks; cap exposed starter bars and keep work areas clear.
⚠️ Use correct manual handling techniques for long bars and mesh sheets; team lift or use plant for heavy lengths.
⚠️ Maintain trench safety at all times. Assess collapse risk, edge stability, access/egress and spoil placement before entry.
⚠️ If excavation depth or soil conditions create a trench hazard, follow site SWMS, temporary works controls, and principal contractor requirements.
⚠️ Keep bar chairs stable and footing trenches free from loose spoil so reinforcement does not shift during concrete placement.
⚠️ Any structural work must follow engineered details. Do not vary bar size, spacing, laps or cover without engineer approval.
⚠️ Compliance should align with AS 3600, footing design documents, soil report recommendations and applicable state/council requirements.

Step-by-Step Guide

Step 1: Review engineering and footing schedule

1️⃣ Confirm structural requirements

Before unloading reo, check the engineer’s footing plan, slab/footing details, general notes and bar bending schedule. Confirm footing width, depth, bar size, quantity, laps, corner details, trench mesh type, starter bar locations and minimum concrete cover.

Verify whether the footing is a strip footing, deepened edge beam, pad footing, stiffening beam or pier/beam arrangement. Do not assume standard site practice applies if the drawings call for specific bar arrangements.

For Australian residential work, reinforcement installation must match the certified engineering drawings and align with AS 3600. If masonry loads are involved, footing performance also ties back to the structural intent under AS 3700 Masonry Structures.

Step 2: Prepare and inspect the trench

2️⃣ Get the excavation ready for reo

The trench must be excavated to correct line, depth and width before reinforcement goes in. Clean out loose soil, slumped material, standing water, roots and debris so bar chairs sit firm and cover can be maintained.

Check the founding surface matches the geotech or engineering intent. Soft spots, over-excavation and disturbed bottoms need rectification before placing steel. If required, install a blinding layer to create a clean, stable base.

Use a laser or dumpy to confirm trench depth along the full run. Footings with variable depth can easily lose cover if the trench bottom is not trimmed properly.

💡 A quick trench check before reo delivery avoids time wasted cutting and assembling cages into non-compliant excavations.

Step 3: Set out reinforcement locations

3️⃣ Mark bar positions and laps

Measure and mark where laps, corners, intersections, step-downs, internal beams, starter bars and any thickened sections occur. For long footing runs, pre-mark lap zones so the crew does not end up with all laps clustered in one section.

Confirm minimum lap lengths from the engineer’s drawings. Where site details are unclear, stop and verify rather than guessing. Lap length varies with bar diameter, concrete strength, bar type and structural design assumptions.

Mark any penetrations, service crossings or dowel locations early. Rework is common when reinforcement is installed before these conflicts are identified.

Step 4: Place bar chairs and spacers

4️⃣ Maintain compliant cover

Install bar chairs or approved spacers at regular centres to support the reinforcement at the required height and maintain bottom cover. Chair spacing depends on bar size, cage weight and footing conditions, but must be close enough to prevent sagging during placement and pour.

For footings cast against ground, cover is often greater than slab work and must be taken from the engineer’s drawings and AS 3600 requirements. On residential jobs, loss of cover is one of the most common defects, especially in muddy trenches or where undersized chairs are used.

Use chairs suited to footing conditions, not light-duty slab chairs. If the base is soft, use wider-footed spacers or provide blinding so the chairs do not punch into the trench bottom.

💡 If the trench base is damp clay or loose fill, concrete or heavy-duty plastic spacers generally perform better than light plastic chairs.

Step 5: Install bottom bars or trench mesh

5️⃣ Place the primary footing reinforcement

Set the bottom longitudinal bars or trench mesh into the trench on the chairs, ensuring straight alignment and specified cover to the trench sides and base. Where using trench mesh, keep it centred within the footing width unless the drawings specify otherwise.

For strip footings, reinforcement typically consists of continuous longitudinal bars, trench mesh, or a formed cage with ligatures. Keep bars off the ground at all times. Reo sitting directly in soil is non-compliant and reduces durability.

Tie bars at intersections and supports using annealed tie wire so the assembly remains stable during inspection and concrete placement. Ties should be secure but do not need to distort or pull bars out of position.

Where multiple bars are required, maintain the specified spacing between bars using spacers, ligatures or cage geometry. Avoid bars touching each other unless the detail specifically permits bundled placement.

Step 6: Form laps, corners and junctions correctly

6️⃣ Tie all continuity details properly

Install lap splices to the exact lengths shown by the engineer. Stagger laps where practical if the detail requires it, and avoid stacking too many splices in one short section unless specifically designed.

At corners and T-junctions, use bent bars, corner bars or overlap details exactly as documented. Straight bars simply butted together at corners are not acceptable unless the engineer has detailed a specific alternative.

Check that lap zones still maintain cover. Congested reinforcement at intersections can easily push steel hard against trench walls, reducing side cover and making concrete placement difficult.

💡 Pre-bending and dry-fitting corner assemblies beside the trench can save time and improve accuracy on complex footing layouts.

Step 7: Install ligatures, stirrups and top bars where required

7️⃣ Complete the cage assembly

Where the footing detail includes ligatures, stirrups or top bars, install these after the bottom steel is located. Tie each component securely so the cage holds its shape during lifting, inspection and the concrete pour.

Check ligature spacing against the drawing, especially near concentrated loads, piers, articulation points or retaining wall sections. Keep all bars within the cage profile so cover is maintained on every face.

For deeper footings, assembled cages may be built beside the trench and lowered in by machine. If doing so, use appropriate lifting points and ensure the cage is not racked or damaged during handling.

Equipment hire for a reo bender or small lifting plant is usually more economical than purchase for occasional footing packages, but high-volume builders may justify owning dedicated reo gear.

Step 8: Fix starter bars, dowels and connections

8️⃣ Prepare for walls, columns or masonry above

Install all starter bars, dowels, L-bars or rod connections shown on the drawings before the pour. Check projection heights, embedment, spacing and alignment carefully, particularly where masonry walls, retaining walls, columns or piers will sit above.

Use templates where needed to maintain spacing and plumb alignment. Unsupported starters often move during concrete placement, leading to expensive rectification.

If reinforcement is to connect to future pours, ensure the exposed length is protected and clearly identified. Fit safety caps to projecting bars immediately after placement.

Step 9: Check cover, levels and tie integrity

9️⃣ Carry out the pre-pour inspection

Before calling for inspection or concrete, walk the entire footing and confirm:

bar size and quantity match drawings
laps are correct and in the right locations
bar chairs are adequate and stable
bottom, side and top cover are maintained
trench is clean and free of loose spoil
all starters, dowels and corner details are installed
ties are secure and the cage cannot float or collapse

Measure cover at representative points. Typical site failures include chairs kicked over, bars hard against trench walls, and mesh sagging between supports.

Where required, arrange builder, certifier or engineer inspection before the pour. Do not allow concrete placement until any hold-point has been released.

Step 10: Support reinforcement during concrete placement

🔟 Keep the reo in position through the pour

During the pour, monitor the reinforcement continuously. Vibrator use, hose drag, concrete discharge and worker traffic can all shift cages and reduce cover if no one is watching.

Place concrete evenly along the footing rather than dumping excessive volume in one spot. Reposition displaced bars immediately while access remains safe and before the concrete stiffens.

For structural footings, concrete quality and placement should comply with AS 3600 and project specifications. If site-mixed concrete is used for minor work, a general-purpose mix is commonly 1:2:3, while structural applications are commonly 1:1.5:2.5—but footing concrete on residential sites is typically supplied as engineered premix to the specified strength class.

Common Mistakes to Avoid

1.Placing reinforcement directly on soil instead of on compliant bar chairs or spacers.
2.Using incorrect lap lengths or clustering all laps in one location without reference to drawings.
3.Letting bars touch trench walls, which reduces concrete cover and durability.
4.Using slab chairs in footing trenches where heavier-duty supports are needed.
5.Failing to secure starter bars and dowels, allowing movement during the pour.

Pro Tips

💡 Build and tie repetitive cage sections beside the trench where access allows, then lower them in for faster installation.
💡 Keep a dedicated crew member on cover checks; footing defects are usually spacing and chair-related, not bar-count related.
💡 Use wider-base spacers in wet or reactive soils to stop chairs punching into the trench bottom.
💡 Mark lap zones with paint before steel placement so the team can work quickly without second-guessing splice locations.
💡 Photograph reinforcement before the pour for QA records, especially at corners, junctions and starter bar locations.

Recommended Tools

Reo tying nips — fast, reliable hand tying for footing cages
Battery rebar tying tool — ideal for larger residential footing runs and repetitive cage work
Portable rebar bender/cutter — efficient for N12–N16 bar fabrication on site
Rotary laser level — accurate footing depth and reinforcement set-out checks
Heavy-duty footing bar chairs — better stability in trench conditions than standard slab chairs

Frequently asked questions

What is the Australian standard for concrete footing reinforcement?
Residential concrete footing reinforcement is governed primarily by AS 2870:2011 (Residential Slabs and Footings) and AS 3600:2018 (Concrete Structures). These standards specify the minimum steel grade (500 MPa), trench mesh configurations, bar chair spacing, and concrete cover necessary to resist ground movement and structural loads.
How much concrete cover is required for footing reinforcement in Australia?
Under AS 2870 and AS 3600, footings cast directly against ground or blinding concrete typically require a minimum concrete cover of 40mm to 50mm. If concrete is poured directly against rough earth without a membrane, cover must increase to at least 65mm or 75mm depending on local soil exposure classifications.
What lap length is required for trench mesh in strip footings?
Trench mesh requires a minimum lap splice length of 500mm for standard residential strip footings under AS 2870, or as specified by the structural engineer. The cross wires must overlap to maintain structural continuity and ensure tensile loads transfer effectively across the splice without causing concrete breakout.
What bar chairs should be used for footing trenches?
Trench footings require heavy-duty plastic trench mesh supports or concrete block spacers rather than lightweight clip-on slab chairs. Plastic trench chairs feature broad, flat bases that prevent the support from sinking into soft trench bed soil under the heavy load of steel reinforcement and foot traffic.
What are the most common footing reinforcement installation mistakes?
The most frequent site defects include placing reo directly on dirt, inadequate side cover from trench wall collapse, insufficient lap lengths, and poor tying of corner bars. Leaving loose soil or slurry under bar chairs also compromises footing depth and leads to premature steel corrosion.
How do you reinforce corners and T-intersections in strip footings?
Corners and T-intersections require dedicated L-shaped corner bars (typically N12 or N16 cogged bars) overlapping each trench mesh run by at least 500mm. Simply butting mesh sheets together at corners creates a structural hinge that will fail under differential soil movement.