How to install reinforcement for concrete footings
Learn how to install reinforcement for concrete footings to AS 2870 and AS 3600. Master trench mesh placement, bar chairs, lap lengths, and concrete cover.
Quick answer
To install reinforcement for concrete footings, suspend trench mesh and deformed bars on compliant plastic chairs at least 50mm above the trench base. Overlap mesh joints by 500mm, tie securely with 1.57mm annealed wire, and maintain 40mm to 65mm clearance from earth walls to meet AS 2870 requirements.
- Skill level
- Advanced
- Time
- 4–8 hours for a standard residential footing run, depending on footing length, complexity, access, and reo schedule
- Trade
- Building & Construction
- Updated
- 1 November 2026
Tools you will need
- Knipex 99 14 250 - High Leverage Concreters Nippers
- Makita DTR180Z 18V LXT - Cordless Rebar Tying Tool
- Ox Tools Pro 5m - Metric Heavy Duty Tape Measure
- Leica Geosystems Rugby 610 - Rotating Construction Laser Level
- Hitachi / HiKOKI 16mm - Electric Rebar Cutter and Bender
- Master Finish 600mm - Heavy Duty Bolt Cutters
- Novoplas Trench Mesh Supports - Plastic Bar Chairs (50/65mm)
What is involved in installing reinforcement for concrete footings in Australia?
🧱 Installing reinforcement for concrete footings is a critical structural task that directly affects load transfer, crack control, and long-term footing performance. On Australian residential sites, correct reo placement requires accurate trench preparation, compliant cover, secure bar support, and installation in line with the engineer’s drawings, AS 3600 Concrete Structures, and relevant NCC and state requirements.
This guide covers practical site procedure for placing trench mesh, longitudinal bars, ligatures, laps, bar chairs and tie wire in strip footings and similar residential footing systems. Structural reinforcement layouts, bar sizes and lap requirements must always match the project engineering documentation.
What skill level is required for concrete footing reinforcement in Australia?
Advanced — Estimated time: 4–8 hours for a standard residential footing run, depending on footing length, complexity, access, and reo schedule
What tools are required for installing concrete footing reinforcement?
What materials are needed for concrete footing reinforcement?
Safety Requirements
Step-by-Step Guide
Step 1: Review engineering and footing schedule
1️⃣ Confirm structural requirements
Before unloading reo, check the engineer’s footing plan, slab/footing details, general notes and bar bending schedule. Confirm footing width, depth, bar size, quantity, laps, corner details, trench mesh type, starter bar locations and minimum concrete cover.
Verify whether the footing is a strip footing, deepened edge beam, pad footing, stiffening beam or pier/beam arrangement. Do not assume standard site practice applies if the drawings call for specific bar arrangements.
For Australian residential work, reinforcement installation must match the certified engineering drawings and align with AS 3600. If masonry loads are involved, footing performance also ties back to the structural intent under AS 3700 Masonry Structures.
Step 2: Prepare and inspect the trench
2️⃣ Get the excavation ready for reo
The trench must be excavated to correct line, depth and width before reinforcement goes in. Clean out loose soil, slumped material, standing water, roots and debris so bar chairs sit firm and cover can be maintained.
Check the founding surface matches the geotech or engineering intent. Soft spots, over-excavation and disturbed bottoms need rectification before placing steel. If required, install a blinding layer to create a clean, stable base.
Use a laser or dumpy to confirm trench depth along the full run. Footings with variable depth can easily lose cover if the trench bottom is not trimmed properly.
💡 A quick trench check before reo delivery avoids time wasted cutting and assembling cages into non-compliant excavations.
Step 3: Set out reinforcement locations
3️⃣ Mark bar positions and laps
Measure and mark where laps, corners, intersections, step-downs, internal beams, starter bars and any thickened sections occur. For long footing runs, pre-mark lap zones so the crew does not end up with all laps clustered in one section.
Confirm minimum lap lengths from the engineer’s drawings. Where site details are unclear, stop and verify rather than guessing. Lap length varies with bar diameter, concrete strength, bar type and structural design assumptions.
Mark any penetrations, service crossings or dowel locations early. Rework is common when reinforcement is installed before these conflicts are identified.
Step 4: Place bar chairs and spacers
4️⃣ Maintain compliant cover
Install bar chairs or approved spacers at regular centres to support the reinforcement at the required height and maintain bottom cover. Chair spacing depends on bar size, cage weight and footing conditions, but must be close enough to prevent sagging during placement and pour.
For footings cast against ground, cover is often greater than slab work and must be taken from the engineer’s drawings and AS 3600 requirements. On residential jobs, loss of cover is one of the most common defects, especially in muddy trenches or where undersized chairs are used.
Use chairs suited to footing conditions, not light-duty slab chairs. If the base is soft, use wider-footed spacers or provide blinding so the chairs do not punch into the trench bottom.
💡 If the trench base is damp clay or loose fill, concrete or heavy-duty plastic spacers generally perform better than light plastic chairs.
Step 5: Install bottom bars or trench mesh
5️⃣ Place the primary footing reinforcement
Set the bottom longitudinal bars or trench mesh into the trench on the chairs, ensuring straight alignment and specified cover to the trench sides and base. Where using trench mesh, keep it centred within the footing width unless the drawings specify otherwise.
For strip footings, reinforcement typically consists of continuous longitudinal bars, trench mesh, or a formed cage with ligatures. Keep bars off the ground at all times. Reo sitting directly in soil is non-compliant and reduces durability.
Tie bars at intersections and supports using annealed tie wire so the assembly remains stable during inspection and concrete placement. Ties should be secure but do not need to distort or pull bars out of position.
Where multiple bars are required, maintain the specified spacing between bars using spacers, ligatures or cage geometry. Avoid bars touching each other unless the detail specifically permits bundled placement.
Step 6: Form laps, corners and junctions correctly
6️⃣ Tie all continuity details properly
Install lap splices to the exact lengths shown by the engineer. Stagger laps where practical if the detail requires it, and avoid stacking too many splices in one short section unless specifically designed.
At corners and T-junctions, use bent bars, corner bars or overlap details exactly as documented. Straight bars simply butted together at corners are not acceptable unless the engineer has detailed a specific alternative.
Check that lap zones still maintain cover. Congested reinforcement at intersections can easily push steel hard against trench walls, reducing side cover and making concrete placement difficult.
💡 Pre-bending and dry-fitting corner assemblies beside the trench can save time and improve accuracy on complex footing layouts.
Step 7: Install ligatures, stirrups and top bars where required
7️⃣ Complete the cage assembly
Where the footing detail includes ligatures, stirrups or top bars, install these after the bottom steel is located. Tie each component securely so the cage holds its shape during lifting, inspection and the concrete pour.
Check ligature spacing against the drawing, especially near concentrated loads, piers, articulation points or retaining wall sections. Keep all bars within the cage profile so cover is maintained on every face.
For deeper footings, assembled cages may be built beside the trench and lowered in by machine. If doing so, use appropriate lifting points and ensure the cage is not racked or damaged during handling.
Equipment hire for a reo bender or small lifting plant is usually more economical than purchase for occasional footing packages, but high-volume builders may justify owning dedicated reo gear.
Step 8: Fix starter bars, dowels and connections
8️⃣ Prepare for walls, columns or masonry above
Install all starter bars, dowels, L-bars or rod connections shown on the drawings before the pour. Check projection heights, embedment, spacing and alignment carefully, particularly where masonry walls, retaining walls, columns or piers will sit above.
Use templates where needed to maintain spacing and plumb alignment. Unsupported starters often move during concrete placement, leading to expensive rectification.
If reinforcement is to connect to future pours, ensure the exposed length is protected and clearly identified. Fit safety caps to projecting bars immediately after placement.
Step 9: Check cover, levels and tie integrity
9️⃣ Carry out the pre-pour inspection
Before calling for inspection or concrete, walk the entire footing and confirm:
Measure cover at representative points. Typical site failures include chairs kicked over, bars hard against trench walls, and mesh sagging between supports.
Where required, arrange builder, certifier or engineer inspection before the pour. Do not allow concrete placement until any hold-point has been released.
Step 10: Support reinforcement during concrete placement
🔟 Keep the reo in position through the pour
During the pour, monitor the reinforcement continuously. Vibrator use, hose drag, concrete discharge and worker traffic can all shift cages and reduce cover if no one is watching.
Place concrete evenly along the footing rather than dumping excessive volume in one spot. Reposition displaced bars immediately while access remains safe and before the concrete stiffens.
For structural footings, concrete quality and placement should comply with AS 3600 and project specifications. If site-mixed concrete is used for minor work, a general-purpose mix is commonly 1:2:3, while structural applications are commonly 1:1.5:2.5—but footing concrete on residential sites is typically supplied as engineered premix to the specified strength class.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
Frequently asked questions
- What is the Australian standard for concrete footing reinforcement?
- Residential concrete footing reinforcement is governed primarily by AS 2870:2011 (Residential Slabs and Footings) and AS 3600:2018 (Concrete Structures). These standards specify the minimum steel grade (500 MPa), trench mesh configurations, bar chair spacing, and concrete cover necessary to resist ground movement and structural loads.
- How much concrete cover is required for footing reinforcement in Australia?
- Under AS 2870 and AS 3600, footings cast directly against ground or blinding concrete typically require a minimum concrete cover of 40mm to 50mm. If concrete is poured directly against rough earth without a membrane, cover must increase to at least 65mm or 75mm depending on local soil exposure classifications.
- What lap length is required for trench mesh in strip footings?
- Trench mesh requires a minimum lap splice length of 500mm for standard residential strip footings under AS 2870, or as specified by the structural engineer. The cross wires must overlap to maintain structural continuity and ensure tensile loads transfer effectively across the splice without causing concrete breakout.
- What bar chairs should be used for footing trenches?
- Trench footings require heavy-duty plastic trench mesh supports or concrete block spacers rather than lightweight clip-on slab chairs. Plastic trench chairs feature broad, flat bases that prevent the support from sinking into soft trench bed soil under the heavy load of steel reinforcement and foot traffic.
- What are the most common footing reinforcement installation mistakes?
- The most frequent site defects include placing reo directly on dirt, inadequate side cover from trench wall collapse, insufficient lap lengths, and poor tying of corner bars. Leaving loose soil or slurry under bar chairs also compromises footing depth and leads to premature steel corrosion.
- How do you reinforce corners and T-intersections in strip footings?
- Corners and T-intersections require dedicated L-shaped corner bars (typically N12 or N16 cogged bars) overlapping each trench mesh run by at least 500mm. Simply butting mesh sheets together at corners creates a structural hinge that will fail under differential soil movement.
Written by Bricko, the Building & Construction specialist at QLD.Tools.